Complete Kitchen Renovation in Suburban Home
Project Overview
Our clients wanted to transform their outdated 1990s kitchen into a modern, functional space perfect for family gatherings and meal preparation. The 200 square foot kitchen needed new everything—from flooring to lighting.
Scope of Work
What We Delivered:
- Complete demolition of existing kitchen down to studs
- Custom cabinetry with soft-close drawers and pull-out organizers
- Quartz countertops in a stunning white marble pattern
- New stainless steel appliances including refrigerator, range, and dishwasher
- Recessed LED lighting for modern ambiance and task lighting
- Subway tile backsplash with coordinating grout
- Luxury vinyl plank flooring that mimics hardwood
- Updated electrical with additional outlets and dedicated appliance circuits
- New plumbing for sink and dishwasher connections
Project Timeline
- Planning & Design: 2 weeks
- Material Procurement: 1 week
- Demolition: 2 days
- Rough-in Work: 3 days
- Installation: 2 weeks
- Final Touches: 3 days
- Total Duration: 6 weeks from start to completion
Challenges Overcome
During demolition, we discovered outdated electrical wiring that needed upgrading to meet current code. We worked with the homeowners to adjust the budget and timeline, completing the additional work without delaying the overall project.
Client Testimonial
“We couldn’t be happier with our new kitchen! The team was professional, kept everything clean, and the attention to detail was outstanding. Our kitchen is now the heart of our home.” — Sarah M.
Results
The finished kitchen increased the home’s value by an estimated $35,000 and provided the clients with a beautiful, functional space they’ll enjoy for decades to come.